What is the primary purpose of sprint planning?

To review past sprints

To establish team roles

To outline the work for the next iteration

The primary purpose of sprint planning is to outline the work for the next iteration. During sprint planning, the Scrum team collaborates to define the sprint goal and determine which items from the product backlog will be selected for the upcoming sprint, based on their capacity and priorities. This process involves breaking down the selected items into manageable tasks, ensuring that everyone has a clear understanding of what needs to be accomplished to achieve the sprint goal.

By focusing on the specific work that will be completed within the sprint, the team creates a shared commitment and clarity, which is crucial for fostering alignment and productivity during the iteration. Establishing this foundation helps to ensure that the team works toward common objectives, ultimately leading to enhanced collaboration and success in delivering value to stakeholders.

Get further explanation with Examzify DeepDiveBeta

To finalize release dates